Crossfunctional Power Plant Dysfunction

The coal-fired Power Plant in North Central Oklahoma had gone from 360 employees in 1987 down to 124 employees on August 1, 1994 after the second downsizing.  Monday morning when we arrived at work, the maintenance department met in the main break room to be told how we were going to survive the loss of 100 employees.  With only 7 electricians left, I kept trying to add up on my fingers how we could possibly keep up with all the work we had to do.

Jasper Christensen stood up and after saying that he understood how we must feel about our present situation, he told us that we will have to each work harder.  I shook my head in disbelief (inside my head only… I didn’t really shake my head, as it was frozen with the same blank stare everyone else was wearing).  I knew we weren’t going to be working harder.  — What does that really mean anyway.  I thought he should have said, “We will each have to work “smarter” because we can’t really work “harder”.  Jasper was a nice person, but he never really was much for words so I gave him a pass on this one.  After all, he never really took a course in motivational speaking.

Jasper Christensen

Jasper Christensen

Interestingly, the three people in charge at the plant, Jasper, Jim Arnold and Bill Green were all 53 years old, and only within 4 months in age from each other.  They all belonged to the “old school way of doing things” (see the post:  “From Pioneers to Power Plant Managers“).  As Jasper continued in his speech I noticed that gone was any talk of working together to achieve our goals.  I immediately felt that we had just rolled back our management to a time before our first downsizing in 1987 when the Evil Plant Manager used to rule the plant with an iron fist.

I felt this way because we were being told how we were going to change everything we do without giving any of our own input.  For instance, we would no longer have a Quality Action Team.  That was disbanded immediately.  We would no longer hold Quality Team meetings (we were also told that the Quality process was not going away, though we couldn’t see how it was going to work).  The Safety Task Force did survive.

We were also told that we would no longer fill out any forms unless they are requested by someone.  It seems that we had over 1,300 forms that were being filled out at the plant and most of them were never being used for anything, so, unless someone requested a form, we wouldn’t just fill them out for the sake of filling them out.  This was actually a good idea.  I know we filled out forms in triplicate each week when we did transformer and substation inspections.  Most of those were never looked at, I’m sure.

It turned out later that we needed only about 400 of the 1300 forms our plant was churning out each month.

We were told we wouldn’t be doing Substation inspections.  That was not our responsibility.  It would be done by the Transmission and Distribution division instead.  I was beginning to see how management was trying to figure out how 7 electricians were going to “work harder”.  The answer at the moment was that we were going to do less.  The purpose of the Substation and Transformer checks each week was to look for problems while they were minor instead of waiting for a catastrophe to happen.

We were told that we were not going to “Gold Plate” our work.  We were going to just do what it took to complete the task without worrying about polishing it up to make it “perfect” (which is what real Power Plant Men do).  Instead we were going to “Farm Fix it”.  I’ll go more into this subject with a separate post.

We were then told that we would no longer have an Electric Shop and an Instrument and Controls shop.  We would from then on all meet in the Mechanical Maintenance shop.  We were not supposed to go to the Electric Shop or the Instrument and Controls shops for breaks because we were all going to be cross-functional.  We are all Maintenance now.  No longer specialized (sort of).

We were going to have four Maintenance teams.  Each one will have mechanics, welders, machinists, electricians and Instrument and controls people.  Each member on each team would learn to do each other’s jobs to a degree.

An electrician will learn how to tack weld.  A mechanic will learn how to run conduit and pull wire.  An instrument and controls person will learn how to use the lathe.  We would each learn enough about each job in order to perform minor tasks in each area without having to call the expert in that skill.

When the meeting was over, we each met with our own foremen.  Alan Kramer was my new foreman.  He used to be a foreman in the Instrument and Controls shop.

Alan Kramer

Alan Kramer

It became apparent that even though Jasper had come across as if everything had already been decided and that this was the way it was going to be, things hadn’t really been ironed out yet.  Actually, this was just a first pass.  The main goal was for us to figure out how to get all the work done that needed to be done.  I was still an electrician and I was still responsible for working on electrical jobs.

One really good part of the new situation was that I was now on the same team as Charles Foster.  We had always been very good friends, but I hadn’t worked on the same team as Charles since my first year as an electrician in 1984, ten years earlier when he was my first foreman in the electric shop (See the post:  “New Home in the Power Plant Electric Shop“).  We were the two electricians on Alan Kramer’s team.

Charles Foster

Charles Foster

Besides the fact that everyone was very bitter over the despicable treatment of our fellow Power Plant Men that were laid off the previous Friday (see the post: “Power Plant Downsizing Disaster and the Left Behinds“), we knew that we had to figure out how to make this new arrangement work.  We knew our upper management was using the old tyrannical style of management, but we also knew that at this point, they needed every one of us.  They couldn’t go around firing us just because we spoke our mind (which was good for me, because, I was still in the process of learning how to keep my mouth shut when that was the most beneficial course of action).

As Dysfunctional as our upper management seemed to be at the moment, our new teams embraced the idea of our new Cross-Functional teams with some minor changes.  First, we still needed to see ourselves as electricians, instrument and controls, machinists, welders and mechanics.  We each had our own “certifications” and expertise that only a person with that trade could perform.

Charles and I would still go to the electric shop in the morning before work began, and during lunch and breaks.  Our electric equipment to perform our job was there, and we still needed to maintain a stock of electric supplies.  The same was true for the Instrument and Controls crew members.

Even today, after having been gone from the Power Plant for 13 1/2 years, the electric shop office phone still has my voice on the voice mail message.  I know, because a couple of years ago, when it was accidentally erased, Tim Foster (Charles Foster’s son), asked me to record a new message so they could put it back on the phone.  I considered that a great honor to be asked by True Power Plant Men to record their voice mail message on the electric shop phone.  The Phone number by the way is:  (405) 553-29??.  Oh.  I can’t remember the last two digits.  🙂

Once the kinks were worked out of the cross-functional team structure, it worked really well.  I just kept thinking…. Boy, if we only had a group of supportive upper management that put their plant first over their own personal power needs, this would be great.  The True Power Plant Men figured out how to work around them, so that in spite of the obstacles, within about 4 years, we had hit our stride.

Let me give you an example of how well the cross-functional teams worked compared to the old conventional way we used to work.  I will start by describing how we used to do things….  Let’s say that a pump breaks down at the coal yard…

Horizontal pump

Horizontal pump

— start here —

An operator creates the Maintenance Order (M.O.).  It is eventually assigned to a crew of mechanics.  (start the clock here).  When they have time, they go to the coal yard to look over the problem.  Yep.  The pump is not working.  They will have to take it back to the shop to fix it.

A Maintenance Order is created for the electricians to unwire the motor.  The electricians receive the maintenance order and prioritize it.  They finally assign it to a team to go work on it.  Say, in one week from the time they received the M.O.  The electrician goes to the control room to request a clearance on the pump.  The next day the electrician unwires the motor.  They complete the maintenance order at the end of the day and send it back up to the A Foreman.

The completed electric maintenance order is sent back to the mechanics letting them know that the motor for the pump has been unwired.  When they receive it, a couple of days later, they schedule some time that week to go work on the pump.  At that time, they bring the motor to the electric shop so that it can be worked on at the same time.

The motor and the pump is worked on some time during the next week.

A machinist is needed to re-sleeve a bearing housing on either the motor or the pump or both.  So, an M.O. is created for the machinist to work on creating a sleeve in an end bell of the motor or the pump.

Gary (Stick) McCain

Gary (Stick) McCain — Machinist Extraordinaire

The electricians inform the mechanics when the motor is ready.  When they are done with the pump, and they have put it back in place, they put the motor back.  Then they create an M.O. for the Machinist to line up the motor and the pump before the coupling is installed.

The Machinists prioritize their work and at some point, let’s say a couple of days, they make it up to the motor and work on aligning the pump and the motor.

During the re-installation, it is decided that a bracket that has worn out needs to be welded back.  So, an M.O. is created for the welders to replace the bracket before the motor can be rewired.

The welders prioritize their work, and in a week (or two) they finally have time to go weld the bracket.

George Clouse

George Clouse – Welding Wizard

They return their M.O. completed to the mechanics who then tell the electricians that they can re-wire the motor.

The electricians prioritize their work and when they have time to go re-wire the motor, they wire it up.  After wiring it, they go to the control room to have the operators help them bump test the motor to make sure it runs in the right direction.  An entire day goes by until the electrician receives a call saying that the operator is ready to bump test the motor.  The electrician and/or mechanic meets the operator at the pump to bump test the motor.  Once this test is performed, the mechanic re-couples the motor.

The electrician then removes his clearance on the pump and it is put back into service.  The M.O.s are completed.

—  End here.  The time it took to repair the pump and put it back in service would commonly take one month —

Now see what happens when you have a cross-functional team working on it….(and be amazed).

— Start here —

The maintenance team receives a ticket (M.O.) from the planner that a pump is broken at the coal yard.  A mechanic goes and looks at it and determines it needs to be repaired.  He calls his Electrician Teammate and tells him that the motor needs to be unwired in order to fix the pump.  The electrician goes to the control room and takes a clearance on the pump.

The electrician then goes to the switchgear and waits for the operator to place the clearance.  When that is completed, the electrician goes to the pump and unwires the motor.  While there, he helps the mechanic pull the motor and put it aside.  The electrician determines there if the motor needs to be worked on.  If possible, it is repaired in place, or the motor is brought to the electric shop at the same time as the pump.  It is determined that the pump needs to be worked on, so they work together to bring it to the shop where the mechanics work on the pump.  Any machinist work is done at that time.

When the pump is being put back in place, the bracket is found broken, so they call the welder on their team who comes up and welds it back on.  The machinist comes with the electrician and the mechanic to align the motor.  The operators are called to bump test the motor.  As soon as the test is over, the coupling is installed.  The clearance is removed and the pump is put back in place.

— End here.  The pump can now be repaired within one week instead of four weeks.  Often the pump can be repaired in days instead of weeks. —

The reason why the cross-functional teams worked so well is that we all had the same priority.  We all had the same job and we had all the skills on our team to do all the work.  This was a fantastic change from working in silos.

This was “Working Smarter”, not “Working Harder”.  Ever since that day when we first learned that we had to “Work Harder” I always cringe when I hear that phrase.  To me, “Working Harder” means, “Working Dumber”.  Today I am a big advocate of Cross-Functional Teams.  I have seen them work successfully.  There was only one catch which I will talk about later.  This worked beautifully, but keep in mind… We had cross-functional teams made of the best Power Plant Men on the planet!  So, I may have a lopsided view of how successful they really work in the general public.

Advertisements

Power Plant Farm Fixing and Risk Management

We were told at the coal-fired Power Plant in North Central Oklahoma that we were going to have to stop doing the excellent job we were used to doing.  We no longer had time to make everything perfect.  We just had to patch things together enough so that it was fixed and leave it at that.  Jasper Christensen told us that we were going to have to “Farm Fix” things and work harder because we now only had half the employees.

Jasper Christensen

Jasper Christensen

Two things bothered me right away….

First, “Work Harder.”  What exactly does that mean?  How does one work harder?  When I pick up my tool bucket to go work on a job, should I put some extra bricks in it so that it is harder to carry?  What then?  Think about it… Shouldn’t we be working “Smarter” instead of “Harder”?  We were all hard workers (if that means, spending a good 8 hour day doing your job).  Any slackers were laid off 7 years earlier.

When I heard “Farm Fixing” I took offense to the reference.  Jasper had mentioned using baling wire to hold something up instead of taking the time to make our jobs look pretty.  As if baling wire was somehow synonymous with “Farm Fixing”.  My grandfather was a farmer….  I’ll talk about that in a bit….

Jasper also informed us that we were no longer stuck doing only our own trade.  So, an electrician should expect to help out as a mechanic or a welder as long as it wasn’t too involved.  Certain welding jobs, for instance, require a certified welder.  If the job was just to tack weld up a bracket somewhere, then I, as an electrician, could wheel a welding machine over there and weld it up.

After that initial meeting after we had been downsized to pint-sized, we met with our own teams.  Alan Kramer was my new foreman.  He encouraged us to learn the different skills from our teammates.

Alan Kramer

Alan Kramer

I asked Ed Shiever to teach me how to weld.  After about an hour, I decided I wasn’t too interested in melting metal using electricity.  I would leave it to the experts.  I was left with a sunburned chest, as I usually wore a V-Neck Tee Shirt in the summer.

Ed Shiever 15 years later

Ed Shiever Welder Extraordinaire

Jody Morse was a mechanic on our team, who had been a friend of mine since I was a janitor.  We had been on the labor crew together.  He asked me if he could do some electrical work with me.  He thought it would be a useful skill to learn.  I happily agreed to let him work alongside me running conduit and pulling wire around the precipitator hoppers.

Jody Morse

Jody Morse

It wouldn’t include working on any circuits where he might accidentally come into contact with anything live.  So, I thought this was a good starting point.  That was one of the first skills I learned as an electrician-in-training when I was taught by Gene Roget, a master of conduit bending.

I showed Jody how to bend the conduit and have it end up being the right length with the curves in the right place (which is a little tricky at first).  Then I showed Jody where the conduit needed to go, and where the wire needed to end up.  He said he wanted to do this all by himself, so I left him to it and left to do something else.

A little while later, Jody came back and said he had a slight problem.  He had cut the cable just a little bit too short (Yeah.  I had done that myself, see the post: “When Enough Power Plant Stuff Just Ain’t Enough“).  I looked at the problem with him, and he was about six inches too short.

Jody looked the job over and decided he had two options.  Pull some new longer cable, or try to make the existing cable work.He figured out that if he cut off 6 inches of the conduit, and sort of bent it out so that it was no longer exactly at 90 degrees, then it would still reach where it needed to go, only the conduit wouldn’t look so pretty because the conduit would appear a little cockeyed.  We figured this would be all right because Jasper had just finished telling us that we needed to make things not so pretty anymore.  Jody finished the job, and filled out the Maintenance Order indicating that the job was done.

The cable and conduit job had been requested by Ron Madron, one of the Instrument and Controls guys on our team.  When he went out and looked at the conduit, let’s just say that he wasn’t too impressed.  He went to Alan Kramer and complained that the conduit job was disgraceful.  I don’t remember his exact words, but when I heard about it, it sounded to me like he said “It was an abomination to all things electrical”.

I had always taken pride in my work, and doing a “sloppy” job was not normal for me.  I didn’t want Jody to feel bad about this because he was pretty proud of having completed the job all by himself without my help.  So I went and had a one-on-one with Ron and explained the situation to him.  I also told him that the next time he has  problem with something I did, come directly and talk to me about it instead of our foreman.  We’re all on the same team now.

I think once he realized the situation, he was more receptive.  Jody and I did go back out there and fix the issue by running a new cable that was long enough, with a new piece of conduit that was installed with the best of care so that it looked pretty.  — None of us informed Jasper that behind his back we were still performing our jobs with great care and precision.

 

Conduit Bending Basics

Conduit Bending Basics

The more I thought about the idea of “Farm Fixing” and “Risk Management” and how it was being applied at our plant, after about a year, I wrote a letter to the Superintendent over all the Power Plants, Jack Coffman.

Here is the letter I wrote (It was titled “Farm Fixing and Risk Management” — appropriate, don’t you think?):

Dear Jack Coffman,

I went through the Root Learning Class on Friday, September 6.  After the class our table remained to discuss with Bruce Scambler the situation that exists at the power plants concerning the way we maintain our equipment.  We attempted to discuss our concerns with our facilitator, however, the canyon depicted in the first visual became more and more evident the further we discussed it.

Roo-Learning-Canyon

The Canyon Root Learning Map

My two concerns are the terms “Farm Fixing” and “Risk Management”.  These are two good processes which I believe must be employed if we are to compete in an open market.  I do believe, however, that our management has misunderstood their true meaning and has turned them into catch phrases that are something totally different than they were originally intended.

I come from a family of farmers.  My father and grandfather were farmers.  I was concerned about our use of the term “Farm-fixed”, so I discussed the way we were using it in our company with my father and I have confirmed my understanding of the term.

My grandfather as a farmer was a Welder, a Blacksmith, a Carpenter, and an Engine Mechanic.  When a piece of machinery broke down while he was out harvesting or plowing a field, it is true that baling wire and a quick fix was needed to continue the work for the day.  There is a small window of opportunity when harvesting and the equipment had to be running during this time or the farmer’s livelihood was at stake.

That evening, however, the piece that broke was reworked and re-machined until it was better than the original store bought item.  Thus guaranteeing that it wouldn’t break down the following day.  If the repairs took all night to make it right, they would stay up all night repairing it correctly.  It was vital to their livelihood to have their machinery running as well as possible.

A Ford Tractor soon became my grandfather’s tractor as the original factory parts were replaced with more sturdy parts.  It wasn’t repainted (gold-plated), because they weren’t planning on selling their equipment.  The tractors and plows would last years longer than originally designed.  All this was before farming became a subsidized industry.

We need to “Farm-Fix” our equipment.  Our management however, focuses on the use of baling wire during an emergency and replaces the true meaning of Farm-Fixing with the meaning of “Jerry-Rigging”.  Which is merely a temporary fix while farming and is NOT farm-fixing something.  We have been maintaining our plant with quick fixes and have not been farm-fixing them.  If so, our equipment would be more reliable, and would last longer than originally intended.

Risk Management is another area that has been misunderstood by our management.  They have gone to school and have been trained in Risk Management.  I don’t believe they are using their tools in the way that they were taught.  They have taken the underlying idea that we may not need to make a change or repair a certain piece of equipment at this particular time and have made it the center of their idea of Risk Management.  Risk Management is more than that.  It is weighing the consequences of both actions against the cost and making an informed decision to determine the timing of maintenance.

Risk Management at our plant has become nothing more than speculation, or what I call “Wish Management”.  The decision is often made based on the immediate cost and downtime to delay maintenance without properly identifying the possible damage that could occur and the cost of that scenario.

The phrase “It’s run that way this long, it will probably be all right” is used to justify not repairing the equipment.  No real analysis is done.  Then we cross our fingers and “Wish” that it will continue running forever.

I believe in the concepts of Risk Management and Farm-fixing.  I think they are processes that should be used in our company to achieve and maintain “Best-In-Class”.  I am concerned, however, that if we continue on the course that we are on where “Wishing” and “Jerry-rigging” are our processes, it will only be a matter of time before our workers get killed and our plants melt down around us.

Kevin Breazile

Sooner Station

— End of the letter.  See?  I was always trying to stir things up.

The first summer I worked at the Power Plant as a summer help, we had a couple of floor drain covers in the maintenance shop that were missing from the floor drains.  Plywood had been used to cover the drains, which had been smashed down by the heavy equipment that traveled in and out of the shop.  One day during lunch I wrote a Maintenance Order to have the floor drain covers replaced and placed it on Marlin McDaniel’s (the only A Foreman at the time) desk.  I was only an 18 year old kid that was just learning my way around in the world and already stirring things up, but I figured this was an accident waiting to happen.

The very next day, a plant mechanic, Tom Dean stepped onto one of those floor drains while carrying a heavy ladder and seriously hurt his back.  It was a life changing event for Tom that immediately changed his career.  The next day, the drains had new covers.  I talked about this in the post:  “Power Plant Safety is Job Number One

Approximately one year after I wrote the Farm-fixing and Risk Management letter to Jack Coffman, we had a major incident at the power plant that was directly caused by the decision not to replace a coupling when it was known to be faulty (risk management, they called it).  It would have required extending an overhaul a day or two.  Instead, after half of the T-G floor burned to the ground and the plant was offline for about 3 months.  Millions of dollars of damage.  That is a story for another post.

Crossfunctional Power Plant Dysfunction

The coal-fired Power Plant in North Central Oklahoma had gone from 360 employees in 1987 down to 124 employees on August 1, 1994 after the second downsizing.  Monday morning when we arrived at work, the maintenance department met in the main break room to be told how we were going to survive the loss of 100 employees.  With only 7 electricians left, I kept trying to add up on my fingers how we could possibly keep up with all the work we had to do.

Jasper Christensen stood up and after saying that he understood how we must feel about our present situation, he told us that we will have to each work harder.  I shook my head in disbelief (inside my head only… I didn’t really shake my head, as it was frozen with the same blank stare everyone else was wearing).  I knew we weren’t going to be working harder.  — What does that really mean anyway.  I thought he should have said, “We will each have to work “smarter” because we can’t really work “harder”.  Jasper was a nice person, but he never really was much for words so I gave him a pass on this one.

Jasper Christensen

Jasper Christensen

Interestingly, the three people in charge at the plant, Jasper, Jim Arnold and Bill Green were all 53 years old, and only within 4 months in age from each other.  They all belonged to the “old school way of doing things” (see the post:  “From Pioneers to Power Plant Managers“).  As Jasper continued in his speech I noticed that gone was any talk of working together to achieve our goals.  I immediately felt that we had just rolled back our management to a time before our first downsizing in 1987 when the Evil Plant Manager used to rule the plant with an iron fist.

I felt this way because we were being told how we were going to change everything we do without giving any of our own input.  For instance, we would no longer have a Quality Action Team.  That was disbanded immediately.  We would no longer hold Quality Team meetings (we were also told that the Quality process was not going away, though we couldn’t see how it was going to work).  The Safety Task Force did survive.

We were also told that we would no longer fill out any forms unless they are requested by someone.  It seems that we had over 1,300 forms that were being filled out at the plant and most of them were never being used for anything, so, unless someone requested a form, we wouldn’t just fill them out for the sake of filling them out.  This was actually a good idea.  I know we filled out forms in triplicate each week when we did transformer and substation inspections.  Most of those were never looked at, I’m sure.

It turned out later that we needed only about 400 of the 1300 forms our plant was churning out each month.

We were told we wouldn’t be doing Substation inspections.  That was not our responsibility.  It would be done by the Transmission and Distribution division instead.  I was beginning to see how management was trying to figure out how 7 electricians were going to “work harder”.  The answer at the moment was that we were going to do less.  The purpose of the Substation and Transformer checks each week was to look for problems while they were minor instead of waiting for a catastrophe to happen.

We were told that we were not going to “Gold Plate” our work.  We were going to just do what it took to complete the task without worrying about polishing it up to make it “perfect” (which is what real Power Plant Men do).  Instead we were going to “Farm Fix it”.  I’ll go more into this subject with a separate post.

We were then told that we would no longer have an Electric Shop and an Instrument and Controls shop.  We would from then on all meet in the Mechanical Maintenance shop.  We were not supposed to go to the Electric Shop or the Instrument and Controls shops for breaks because we were all going to be cross-functional.  We are all Maintenance now.  No longer specialized (sort of).

We were going to have four Maintenance teams.  Each one will have mechanics, welders, machinists, electricians and Instrument and controls people.  Each member on each team would learn to do each other’s jobs to a degree.

An electrician will learn how to tack weld.  A mechanic will learn how to run conduit and pull wire.  An instrument and controls person will learn how to use the lathe.  We would each learn enough about each job in order to perform minor tasks in each area without having to call the expert in that skill.

When the meeting was over, we each met with our own foremen.  Alan Kramer was my new foreman.  He used to be a foreman in the Instrument and Controls shop.

Alan Kramer

Alan Kramer

It became apparent that even though Jasper had come across as if everything had already been decided and that this was the way it was going to be, things hadn’t really been ironed out yet.  Actually, this was just a first pass.  The main goal was for us to figure out how to get all the work done that needed to be done.  I was still an electrician and I was still responsible for working on electrical jobs.

One really good part of the new situation was that I was now on the same team as Charles Foster.  We had always been very good friends, but I hadn’t worked on the same team as Charles since my first year as an electrician in 1984, ten years earlier when he was my first foreman in the electric shop (See the post:  “New Home in the Power Plant Electric Shop“).  We were the two electricians on Alan Kramer’s team.

Charles Foster

Charles Foster

Besides the fact that everyone was very bitter over the despicable treatment of our fellow Power Plant Men that were laid off the previous Friday (see the post: “Power Plant Downsizing Disaster and the Left Behinds“), we knew that we had to figure out how to make this new arrangement work.  We knew our upper management was using the old tyrannical style of management, but we also knew that at this point, they needed every one of us.  They couldn’t go around firing us just because we spoke our mind (which was good for me, because, I was still in the process of learning how to keep my mouth shut when that was the most beneficial course of action).

As Dysfunctional as our upper management seemed to be at the moment, our new teams embraced the idea of our new Cross-Functional teams with some minor changes.  First, we still needed to see ourselves as electricians, instrument and controls, machinists, welders and mechanics.  We each had our own “certifications” and expertise that only a person with that trade could perform.

Charles and I would still go to the electric shop in the morning before work began, and during lunch and breaks.  Our electric equipment to perform our job was there, and we still needed to maintain a stock of electric supplies.  The same was true for the Instrument and Controls crew members.

Even today, after having been gone from the Power Plant for 13 1/2 years, the electric shop office phone still has my voice on the voice mail message.  I know, because a couple of years ago, when it was accidentally erased, Tim Foster (Charles Foster’s son), asked me to record a new message so they could put it back on the phone.  I considered that a great honor to be asked by True Power Plant Men to record their voice mail message on the electric shop phone.  The Phone number by the way is:  (405) 553-29??.  Oh.  I can’t remember the last two digits.  🙂

Once the kinks were worked out of the cross-functional team structure, it worked really well.  I just kept thinking…. Boy, if we only had a group of supportive upper management that put their plant first over their own personal power needs, this would be great.  The True Power Plant Men figured out how to work around them, so that in spite of the obstacles, within about 4 years, we had hit our stride.

Let me give you an example of how well the cross-functional teams worked compared to the old conventional way we used to work.  I will start by describing how we used to do things….  Let’s say that a pump breaks down at the coal yard…

Horizontal pump

Horizontal pump

— start here —

An operator creates the Maintenance Order (M.O.).  It is eventually assigned to a crew of mechanics.  (start the clock here).  When they have time, they go to the coal yard to look over the problem.  Yep.  The pump is not working.  They will have to take it back to the shop to fix it.

A Maintenance Order is created for the electricians to unwire the motor.  The electricians receive the maintenance order and prioritize it.  They finally assign it to a team to go work on it.  Say, in one week from the time they received the M.O.  The electrician goes to the control room to request a clearance on the pump.  The next day the electrician unwires the motor.  They complete the maintenance order at the end of the day and send it back up to the A Foreman.

The completed electric maintenance order is sent back to the mechanics letting them know that the motor for the pump has been unwired.  When they receive it, a couple of days later, they schedule some time that week to go work on the pump.  At that time, they bring the motor to the electric shop so that it can be worked on at the same time.

The motor and the pump is worked on some time during the next week.

A machinist is needed to re-sleeve a bearing housing on either the motor or the pump or both.  So, an M.O. is created for the machinist to work on creating a sleeve in an end bell of the motor or the pump.

Gary (Stick) McCain

Gary (Stick) McCain — Machinist Extraordinaire

The electricians inform the mechanics when the motor is ready.  When they are done with the pump, and they have put it back in place, they put the motor back.  Then they create an M.O. for the Machinist to line up the motor and the pump before the coupling is installed.

The Machinists prioritize their work and at some point, let’s say a couple of days, they make it up to the motor and work on aligning the pump and the motor.

During the re-installation, it is decided that a bracket that has worn out needs to be welded back.  So, an M.O. is created for the welders to replace the bracket before the motor can be rewired.

The welders prioritize their work, and in a week (or two) they finally have time to go weld the bracket.

George Clouse

George Clouse – Welding Wizard

They return their M.O. completed to the mechanics who then tell the electricians that they can re-wire the motor.

The electricians prioritize their work and when they have time to go re-wire the motor, they wire it up.  After wiring it, they go to the control room to have the operators help them bump test the motor to make sure it runs in the right direction.  An entire day goes by until the electrician receives a call saying that the operator is ready to bump test the motor.  The electrician and/or mechanic meets the operator at the pump to bump test the motor.  Once this test is performed, the mechanic re-couples the motor.

The electrician then removes his clearance on the pump and it is put back into service.  The M.O.s are completed.

—  End here.  The time it took to repair the pump and put it back in service would commonly take one month —

Now see what happens when you have a cross-functional team working on it….(and be amazed).

— Start here —

The maintenance team receives a ticket (M.O.) from the planner that a pump is broken at the coal yard.  A mechanic goes and looks at it and determines it needs to be repaired.  He calls his Electrician Teammate and tells him that the motor needs to be unwired in order to fix the pump.  The electrician goes to the control room and takes a clearance on the pump.

The electrician then goes to the switchgear and waits for the operator to place the clearance.  When that is completed, the electrician goes to the pump and unwires the motor.  While there, he helps the mechanic pull the motor and put it aside.  The electrician determines there if the motor needs to be worked on.  If possible, it is repaired in place, or the motor is brought to the electric shop at the same time as the pump.  It is determined that the pump needs to be worked on, so they work together to bring it to the shop where the mechanics work on the pump.  Any machinist work is done at that time.

When the pump is being put back in place, the bracket is found broken, so they call the welder on their team who comes up and welds it back on.  The machinist comes with the electrician and the mechanic to align the motor.  The operators are called to bump test the motor.  As soon as the test is over, the coupling is installed.  The clearance is removed and the pump is put back in place.

— End here.  The pump can now be repaired within one week instead of four weeks.  Often the pump can be repaired in days instead of weeks. —

The reason why the cross-functional teams worked so well is that we all had the same priority.  We all had the same job and we had all the skills on our team to do all the work.  This was a fantastic change from working in silos.

This was “Working Smarter”, not “Working Harder”.  Ever since that day when we first learned that we had to “Work Harder” I always cringe when I hear that phrase.  To me, “Working Harder” means, “Working Dumber”.  Today I am a big advocate of Cross-Functional Teams.  I have seen them work successfully.  There was only one catch which I will talk about later.  This worked beautifully, but keep in mind… We had cross-functional teams made of the best Power Plant Men on the planet!  So, I may have a lopsided view of how successful they really work in the general public.

Power Plant Farm Fixing and Risk Management

We were told at the coal-fired Power Plant in North Central Oklahoma that we were going to have to stop doing the excellent job we were used to doing.  We no longer had time to make everything perfect.  We just had to patch things together enough so that it was fixed and leave it at that.  Jasper Christensen told us that we were going to have to “Farm Fix” things and work harder because we now only had half the employees.

Jasper Christensen

Jasper Christensen

Two things bothered me right away….

First, “Work Harder.”  What exactly does that mean?  How does one work harder?  When I pick up my tool bucket to go work on a job, should I put some extra bricks in it so that it is harder to carry?  What then?  Think about it… Shouldn’t we be working “Smarter” instead of “Harder”?  We were all hard workers (if that means, spending a good 8 hour day doing your job).  Any slackers were laid off 7 years earlier.

When I heard “Farm Fixing” I took offense to the reference.  Jasper had mentioned using baling wire to hold something up instead of taking the time to make our jobs look pretty.  As if baling wire was somehow synonymous with “Farm Fixing”.  My grandfather was a farmer….  I’ll talk about that in a bit….

Jasper also informed us that we were no longer stuck doing only our own trade.  So, an electrician should expect to help out as a mechanic or a welder as long as it wasn’t too involved.  Certain welding jobs, for instance, require a certified welder.  If the job was just to tack weld up a bracket somewhere, then I, as an electrician, could wheel a welding machine over there and weld it up.

After that initial meeting after we had been downsized to pint-sized, we met with our own teams.  Alan Kramer was my new foreman.  He encouraged us to learn the different skills from our teammates.

Alan Kramer

Alan Kramer

I asked Ed Shiever to teach me how to weld.  After about an hour, I decided I wasn’t too interested in melting metal using electricity.  I would leave it to the experts.  I was left with a sunburned chest, as I usually wore a V-Neck Tee Shirt in the summer.

Ed Shiever 15 years later

Ed Shiever Welder Extraordinaire

Jody Morse was a mechanic on our team, who had been a friend of mine since I was a janitor.  We had been on the labor crew together.  He asked me if he could do some electrical work with me.  He thought it would be a useful skill to learn.  I happily agreed to let him work alongside me running conduit and pulling wire around the precipitator hoppers.

Jody Morse

Jody Morse

It wouldn’t include working on any circuits where he might accidentally come into contact with anything live.  So, I thought this was a good starting point.  That was one of the first skills I learned as an electrician-in-training when I was taught by Gene Roget, a master of conduit bending.

I showed Jody how to bend the conduit and have it end up being the right length with the curves in the right place (which is a little tricky at first).  Then I showed Jody where the conduit needed to go, and where the wire needed to end up.  He said he wanted to do this all by himself, so I left him to it and left to do something else.

A little while later, Jody came back and said he had a slight problem.  He had cut the cable just a little bit too short (Yeah.  I had done that myself, see the post: “When Enough Power Plant Stuff Just Ain’t Enough“).  I looked at the problem with him, and he was about six inches too short.

Jody looked the job over and decided he had two options.  Pull some new longer cable, or try to make the existing cable work.He figured out that if he cut off 6 inches of the conduit, and sort of bent it out so that it was no longer exactly at 90 degrees, then it would still reach where it needed to go, only the conduit wouldn’t look so pretty because the conduit would appear a little cockeyed.  We figured this would be all right because Jasper had just finished telling us that we needed to make things not so pretty anymore.  Jody finished the job, and filled out the Maintenance Order indicating that the job was done.

The cable and conduit job had been requested by Ron Madron, one of the Instrument and Controls guys on our team.  When he went out and looked at the conduit, let’s just say that he wasn’t too impressed.  He went to Alan Kramer and complained that the conduit job was disgraceful.  I don’t remember his exact words, but when I heard about it, it sounded to me like he said “It was an abomination to all things electrical”.

I had always taken pride in my work, and doing a “sloppy” job was not normal for me.  I didn’t want Jody to feel bad about this because he was pretty proud of having completed the job all by himself without my help.  So I went and had a one-on-one with Ron and explained the situation to him.  I also told him that the next time he has  problem with something I did, come directly and talk to me about it instead of our foreman.  We’re all on the same team now.

I think once he realized the situation, he was more receptive.  Jody and I did go back out there and fix the issue by running a new cable that was long enough, with a new piece of conduit that was installed with the best of care so that it looked pretty.  — None of us informed Jasper that behind his back we were still performing our jobs with great care and precision.

 

Conduit Bending Basics

Conduit Bending Basics

The more I thought about the idea of “Farm Fixing” and “Risk Management” and how it was being applied at our plant, after about a year, I wrote a letter to the Superintendent over all the Power Plants, Jack Coffman.

Here is the letter I wrote (It was titled “Farm Fixing and Risk Management” — appropriate, don’t you think?):

Dear Jack Coffman,

I went through the Root Learning Class on Friday, September 6.  After the class our table remained to discuss with Bruce Scambler the situation that exists at the power plants concerning the way we maintain our equipment.  We attempted to discuss our concerns with our facilitator, however, the canyon depicted in the first visual became more and more evident the further we discussed it.

Roo-Learning-Canyon

The Canyon Root Learning Map

My two concerns are the terms “Farm Fixing” and “Risk Management”.  These are two good processes which I believe must be employed if we are to compete in an open market.  I do believe, however, that our management has misunderstood their true meaning and has turned them into catch phrases that are something totally different than they were originally intended.

I come from a family of farmers.  My father and grandfather were farmers.  I was concerned about our use of the term “Farm-fixed”, so I discussed the way we were using it in our company with my father and I have confirmed my understanding of the term.

My grandfather as a farmer was a Welder, a Blacksmith, a Carpenter, and an Engine Mechanic.  When a piece of machinery broke down while he was out harvesting or ploughing a field, it is true that baling wire and a quick fix was needed to continue the work for the day.  There is a small window of opportunity when harvesting and the equipment had to be running during this time or the farmer’s livelihood was at stake.

That evening, however, the piece that broke was reworked and re-machined until it was better than the original store bought item.  Thus guaranteeing that it wouldn’t break down the following day.  If the repairs took all night to make it right, they would stay up all night repairing it correctly.  It was vital to their livelihood to have their machinery running as well as possible.

A Ford Tractor soon became my grandfather’s tractor as the original factory parts were replaced with more sturdy parts.  It wasn’t repainted (gold-plated), because they weren’t planning on selling their equipment.  The tractors and plows would last years longer than originally designed.  All this was before farming became a subsidized industry.

We need to “Farm-Fix” our equipment.  Our management however, focuses on the use of baling wire during an emergency and replaces the true meaning of Farm-Fixing with the meaning of “Jerry-Rigging”.  Which is merely a temporary fix while farming and is NOT farm-fixing something.  We have been maintaining our plant with quick fixes and have not been farm-fixing them.  If so, our equipment would be more reliable, and would last longer than originally intended.

Risk Management is another area that has been misunderstood by our management.  They have gone to school and have been trained in Risk Management.  I don’t believe they are using their tools in the way that they were taught.  They have taken the underlying idea that we may not need to make a change or repair a certain piece of equipment at this particular time and have made it the center of their idea of Risk Management.  Risk Management is more than that.  It is weighing the consequences of both actions against the cost and making an informed decision to determine the timing of maintenance.

Risk Management at our plant has become nothing more than speculation, or what I call “Wish Management”.  The decision is often made based on the immediate cost and downtime to delay maintenance without properly identifying the possible damage that could occur and the cost of that scenario.

The phrase “It’s run that way this long, it will probably be all right” is used to justify not repairing the equipment.  No real analysis is done.  Then we cross our fingers and “Wish” that it will continue running forever.

I believe in the concepts of Risk Management and Farm-fixing.  I think they are processes that should be used in our company to achieve and maintain “Best-In-Class”.  I am concerned, however, that if we continue on the course that we are on where “Wishing” and “Jerry-rigging” are our processes, it will only be a matter of time before our workers get killed and our plants melt down around us.

Kevin Breazile

Sooner Station

— End of the letter.  See?  I was always trying to stir things up.

The first summer I worked at the Power Plant as a summer help, we had a couple of floor drain covers in the maintenance shop that were missing from the floor drains.  Plywood had been used to cover the drains, which had been smashed down by the heavy equipment that traveled in and out of the shop.  One day during lunch I wrote a Maintenance Order to have the floor drain covers replaced and placed it on Marlin McDaniel’s (the only A Foreman at the time) desk.  I was only an 18 year old kid that was just learning my way around in the world and already stirring things up, but I figured this was an accident waiting to happen.

The very next day, a plant mechanic, Tom Dean stepped onto one of those floor drains while carrying a heavy ladder and seriously hurt his back.  It was a life changing event for Tom that immediately changed his career.  The next day, the drains had new covers.  I talked about this in the post:  “Power Plant Safety is Job Number One

Approximately one year after I wrote the Farm-fixing and Risk Management letter to Jack Coffman, we had a major incident at the power plant that was directly caused by the decision not to replace a coupling when it was known to be faulty (risk management, they called it).  It would have required extending an overhaul a day or two.  Instead, after half of the T-G floor burned to the ground and the plant was offline for about 3 months.  Millions of dollars of damage.  That is a story for another post.

Power Plant Farm Fixing and Risk Management

We were told at the coal-fired Power Plant in North Central Oklahoma that we were going to have to stop doing the excellent job we were used to doing.  We no longer had time to make everything perfect.  We just had to patch things together enough so that it was fixed and leave it at that.  Jasper Christensen told us that we were going to have to “Farm Fix” things and work harder because we now only had half the employees.

Jasper Christensen

Jasper Christensen

Two things bothered me right away….

First, “Work Harder.”  What exactly does that mean?  How does one work harder?  When I pick up my tool bucket to go work on a job, should I put some extra bricks in it so that it is harder to carry?  What then?  Think about it… Shouldn’t we be working “Smarter” instead of “Harder”?  We were all hard workers (if that means, spending a good 8 hour day doing your job).  Any slackers were laid off 7 years earlier.

When I heard “Farm Fixing” I took offense to the reference.  Jasper had mentioned using bailing wire to hold something up instead of taking the time to make our jobs look pretty.  As if bailing wire was somehow synonymous with “Farm Fixing”.  My grandfather was a farmer….  I’ll talk about that in a bit….

Jasper also informed us that we were no longer stuck doing only our own trade.  So, an electrician should expect to help out as a mechanic or a welder as long as it wasn’t too involved.  Certain welding jobs, for instance, require a certified welder.  If the job was just to tack weld up a bracket somewhere, then I, as an electrician, could wheel a welding machine over there and weld it up.

After that initial meeting after we had been downsized to pint-sized, we met with our own teams.  Alan Kramer was my new foreman.  He encouraged us to learn the different skills from our teammates.

Alan Kramer

Alan Kramer

I asked Ed Shiever to teach me how to weld.  After about an hour, I decided I wasn’t too interested in melting metal using electricity.  I would leave it to the experts.  I was left with a sunburned chest, as I usually wore a V-Neck Tee Shirt in the summer.

Ed Shiever 15 years later

Ed Shiever Welder Extraordinaire

Jody Morse was a mechanic on our team, who had been a friend of mine since I was a janitor.  We had been on the labor crew together.  He asked me if he could do some electrical work with me.  He thought it would be a useful skill to learn.  I happily agreed to let him work alongside me running conduit and pulling wire around the precipitator hoppers.

Jody Morse

Jody Morse

It wouldn’t include working on any circuits where he might accidentally come into contact with anything live.  So, I thought this was a good starting point.  That was one of the first skills I learned as an electrician-in-training when I was taught by Gene Roget, a master of conduit bending.

I showed Jody how to bend the conduit and have it end up being the right length with the curves in the right place (which is a little tricky at first).  Then I showed Jody where the conduit needed to go, and where the wire needed to end up.  He said he wanted to do this all by himself, so I left him to it and left to do something else.

A little while later, Jody came back and said he had a slight problem.  He had cut the cable just a little bit too short (Yeah.  I had done that myself, see the post: “When Enough Power Plant Stuff Just Ain’t Enough“).  I looked at the problem with him, and he was about six inches too short.

Jody looked the job over and decided he had two options.  Pull some new longer cable, or try to make the existing cable work.He figured out that if he cut off 6 inches of the conduit, and sort of bent it out so that it was no longer exactly at 90 degrees, then it would still reach where it needed to go, only the conduit wouldn’t look so pretty because the conduit would appear a little cockeyed.  We figured this would be all right because Jasper had just finished telling us that we needed to make things not so pretty anymore.  Jody finished the job, and filled out the Maintenance Order indicating that the job was done.

The cable and conduit job had been requested by Ron Madron, one of the Instrument and Controls guys on our team.  When he went out and looked at the conduit, let’s just say that he wasn’t too impressed.  He went to Alan Kramer and complained that the conduit job was disgraceful.  I don’t remember his exact words, but when I heard about it, it sounded to me like he said “It was an abomination to all things electrical”.

I had always taken pride in my work, and doing a “sloppy” job was not normal for me.  I didn’t want Jody to feel bad about this because he was pretty proud of having completed the job all by himself without my help.  So I went and had a one-on-one with Ron and explained the situation to him.  I also told him that the next time he has  problem with something I did, come directly and talk to me about it instead of our foreman.  We’re all on the same team now.

I think once he realized the situation, he was more receptive.  Jody and I did go back out there and fix the issue by running a new cable that was long enough, with a new piece of conduit that was installed with the best of care so that it looked pretty.  — None of us informed Jasper that behind his back we were still performing our jobs with great care and precision.

 

Conduit Bending Basics

Conduit Bending Basics

The more I thought about the idea of “Farm Fixing” and “Risk Management” and how it was being applied at our plant, after about a year, I wrote a letter to the Superintendent over all the Power Plants, Jack Coffman.

Here is the letter I wrote (It was titled “Farm Fixing and Risk Management” — appropriate, don’t you think?):

Dear Jack Coffman,

I went through the Root Learning Class on Friday, September 6.  After the class our table remained to discuss with Bruce Scambler the situation that exists at the power plants concerning the way we maintain our equipment.  We attempted to discuss our concerns with our facilitator, however, the canyon depicted in the first visual became more and more evident the further we discussed it.

My two concerns are the terms “Farm Fixing” and “Risk Management”.  These are two good processes which I believe must be employed if we are to compete in an open market.  I do believe, however, that our management has misunderstood their true meaning and has turned them into catch phrases that are something totally different than they were originally intended.

I come from a family of farmers.  My father and grandfather were farmers.  I was concerned about our use of the term “Farm-fixed”, so I discussed the way we were using it in our company with my father and I have confirmed my understanding of the term.

My grandfather as a farmer was a Welder, a Blacksmith, a Carpenter, and an Engine Mechanic.  When a piece of machinery broke down while he was out harvesting or ploughing a field, it is true that baling wire and a quick fix was needed to continue the work for the day.  There is a small window of opportunity when harvesting and the equipment had to be running during this time or the farmer’s livelihood was at stake.

That evening, however, the piece that broke was reworked and re-machined until it was better than the original store bought item.  Thus guaranteeing that it wouldn’t break down the following day.  If the repairs took all night to make it right, they would stay up all night repairing it correctly.  It was vital to their livelihood to have their machinery running as well as possible.

A Ford Tractor soon became my grandfather’s tractor as the original factory parts were replaced with more sturdy parts.  It wasn’t repainted (gold-plated), because they weren’t planning on selling their equipment.  The tractors and plows would last years longer than originally designed.  All this was before farming became a subsidized industry.

We need to “Farm-Fix” our equipment.  Our management however, focuses on the use of baling wire during an emergency and replaces the true meaning of Farm-Fixing with the meaning of “Jerry-Rigging”.  Which is merely a temporary fix while farming and is NOT farm-fixing something.  We have been maintaining our plant with quick fixes and have not been farm-fixing them.  If so, our equipment would be more reliable, and would last longer than originally intended.

Risk Management is another area that has been misunderstood by our management.  They have gone to school and have been trained in Risk Management.  I don’t believe they are using their tools in the way that they were taught.  They have taken the underlying idea that we may not need to make a change or repair a certain piece of equipment at this particular time and have made it the center of their idea of Risk Management.  Risk Management is more than that.  It is weighing the consequences of both actions against the cost and making an informed decision to determine the timing of maintenance.

Risk Management at our plant has become nothing more than speculation, or what I call “Wish Management”.  The decision is often made based on the immediate cost and downtime to delay maintenance without properly identifying the possible damage that could occur and the cost of that scenario.

The phrase “It’s run that way this long, it will probably be all right” is used to justify not repairing the equipment.  No real analysis is done.  Then we cross our fingers and “Wish” that it will continue running forever.

I believe in the concepts of Risk Management and Farm-fixing.  I think they are processes that should be used in our company to achieve and maintain “Best-In-Class”.  I am concerned, however, that if we continue on the course that we are on where “Wishing” and “Jerry-rigging” are our processes, it will only be a matter of time before our workers get killed and our plants melt down around us.

Kevin Breazile

Sooner Station

— End of the letter.  See?  I was always trying to stir things up.

The first summer I worked at the Power Plant as a summer help, we had a couple of floor drain covers in the maintenance shop that were missing from the floor drains.  Plywood had been used to cover the drains, which had been smashed down by the heavy equipment that traveled in and out of the shop.  One day during lunch I wrote a Maintenance Order to have the floor drain covers replaced and placed it on Marlin McDaniel’s (the only A Foreman at the time) desk.  I was only an 18 year old kid that was just learning my way around in the world and already stirring things up, but I figured this was an accident waiting to happen.

The very next day, a plant mechanic, Tom Dean stepped onto one of those floor drains while carrying a heavy ladder and seriously hurt his back.  It was a life changing event for Tom that immediately changed his career.  The next day, the drains had new covers.  I talked about this in the post:  “Power Plant Safety is Job Number One

Approximately one year after I wrote the Farm-fixing and Risk Management letter to Jack Coffman, we had a major incident at the power plant that was directly caused by the decision not to replace a coupling when it was known to be faulty (risk management, they called it).  It would have required extending an overhaul a day or two.  Instead, after half of the T-G floor burned to the ground and the plant was offline for about 3 months.  Millions of dollars of damage.  That is a story for another post.

Crossfunctional Power Plant Dysfunction

The coal-fired Power Plant in North Central Oklahoma had gone from 360 employees in 1987 down to 124 employees on August 1, 1994 after the second downsizing.  Monday morning when we arrived at work, the maintenance department met in the main break room to be told how we were going to survive the loss of 100 employees.  With only 7 electricians left, I kept trying to add up on my fingers how we could possibly keep up with all the work we had to do.

Jasper Christensen stood up and after saying that he understood how we must feel about our present situation, he told us that we will have to each work harder.  I shook my head in disbelief (inside my head only… I didn’t really shake my head, as it was frozen with the same blank stare everyone else was wearing).  I knew we weren’t going to be working harder.  — What does that really mean anyway.  I thought he should have said, “We will each have to work “smarter” because we can’t really work “harder”.  Jasper was a nice person, but he never really was much for words so I gave him a pass on this one.

Jasper Christensen

Jasper Christensen

Interestingly, the three people in charge at the plant, Jasper, Jim Arnold and Bill Green were all 53 years old, and only within 4 months in age from each other.  They all belonged to the “old school way of doing things” (see the post:  “From Pioneers to Power Plant Managers“).  As Jasper continued in his speech I noticed that gone was any talk of working together to achieve our goals.  I immediately felt that we had just rolled back our management to a time before our first downsizing in 1987 when the Evil Plant Manager used to rule the plant with an iron fist.

I felt this way because we were being told how we were going to change everything we do without giving any of our own input.  For instance, we would no longer have a Quality Action Team.  That was disbanded immediately.  We would no longer hold Quality Team meetings (we were also told that the Quality process was not going away, though we couldn’t see how it was going to work).  The Safety Task Force did survive.

We were also told that we would no longer fill out any forms unless they are requested by someone.  It seems that we had over 1,300 forms that were being filled out at the plant and most of them were never being used for anything, so, unless someone requested a form, we wouldn’t just fill them out for the sake of filling them out.  This was actually a good idea.  I know we filled out forms in triplicate each week when we did transformer and substation inspections.  Most of those were never looked at, I’m sure.

It turned out later that we needed only about 400 of the 1300 forms our plant was churning out each month.

We were told we wouldn’t be doing Substation inspections.  That was not our responsibility.  It would be done by the Transmission and Distribution division instead.  I was beginning to see how management was trying to figure out how 7 electricians were going to “work harder”.  The answer at the moment was that we were going to do less.  The purpose of the Substation and Transformer checks each week was to look for problems while they were minor instead of waiting for a catastrophe to happen.

We were told that we were not going to “Gold Plate” our work.  We were going to just do what it took to complete the task without worrying about polishing it up to make it “perfect” (which is what real Power Plant Men do).  Instead we were going to “Farm Fix it”.  I’ll go more into this subject with a separate post.

We were then told that we would no longer have an Electric Shop and an Instrument and Controls shop.  We would from then on all meet in the Mechanical Maintenance shop.  We were not supposed to go to the Electric Shop or the Instrument and Controls shops for breaks because we were all going to be cross-functional.  We are all Maintenance now.  No longer specialized (sort of).

We were going to have four Maintenance teams.  Each one will have mechanics, welders, machinists, electricians and Instrument and controls people.  Each member on each team would learn to do each other’s jobs to a degree.

An electrician will learn how to tack weld.  A mechanic will learn how to run conduit and pull wire.  An instrument and controls person will learn how to use the lathe.  We would each learn enough about each job in order to perform minor tasks in each area without having to call the expert in that skill.

When the meeting was over, we each met with our own foremen.  Alan Kramer was my new foreman.  He used to be a foreman in the Instrument and Controls shop.

Alan Kramer

Alan Kramer

It became apparent that even though Jasper had come across as if everything had already been decided and that this was the way it was going to be, things hadn’t really been ironed out yet.  Actually, this was just a first pass.  The main goal was for us to figure out how to get all the work done that needed to be done.  I was still an electrician and I was still responsible for working on electrical jobs.

One really good part of the new situation was that I was now on the same team as Charles Foster.  We had always been very good friends, but I hadn’t worked on the same team as Charles since my first year as an electrician in 1984, ten years earlier when he was my first foreman in the electric shop (See the post:  “New Home in the Power Plant Electric Shop“).  We were the two electricians on Alan Kramer’s team.

Charles Foster

Charles Foster

Besides the fact that everyone was very bitter over the despicable treatment of our fellow Power Plant Men that were laid off the previous Friday (see the post: “Power Plant Downsizing Disaster and the Left Behinds“), we knew that we had to figure out how to make this new arrangement work.  We knew our upper management was using the old tyrannical style of management, but we also knew that at this point, they needed every one of us.  They couldn’t go around firing us just because we spoke our mind (which was good for me, because, I was still in the process of learning how to keep my mouth shut when that was the most beneficial course of action).

As Dysfunctional as our upper management seemed to be at the moment, our new teams embraced the idea of our new Cross-Functional teams with some minor changes.  First, we still needed to see ourselves as electricians, instrument and controls, machinists, welders and mechanics.  We each had our own “certifications” and expertise that only a person with that trade could perform.

Charles and I would still go to the electric shop in the morning before work began, and during lunch and breaks.  Our electric equipment to perform our job was there, and we still needed to maintain a stock of electric supplies.  The same was true for the Instrument and Controls crew members.

Even today, after having been gone from the Power Plant for 13 1/2 years, the electric shop office phone still has my voice on the voice mail message.  I know, because a couple of years ago, when it was accidentally erased, Tim Foster (Charles Foster’s son), asked me to record a new message so they could put it back on the phone.  I considered that a great honor to be asked by True Power Plant Men to record their voice mail message on the electric shop phone.  The Phone number by the way is:  (405) 553-29??.  Oh.  I can’t remember the last two digits.  🙂

Once the kinks were worked out of the cross-functional team structure, it worked really well.  I just kept thinking…. Boy, if we only had a group of supportive upper management that put their plant first over their own personal power needs, this would be great.  The True Power Plant Men figured out how to work around them, so that in spite of the obstacles, within about 4 years, we had hit our stride.

Let me give you an example of how well the cross-functional teams worked compared the old conventional way we used to work.  I will start by describing how we used to do things….  Let’s say that a pump breaks down at the coal yard…

Horizontal pump

Horizontal pump

— start here —

An operator creates the Maintenance Order (M.O.).  It is eventually assigned to a crew of mechanics.  (start the clock here).  When they have time, they go to the coal yard to look over the problem.  Yep.  The pump is not working.  They will have to take it back to the shop to fix it.

A Maintenance Order is created for the electricians to unwire the motor.  The electricians receive the maintenance order and prioritize it.  They finally assign it to a team to go work on it.  Say, in one week from the time they received the M.O.  The electrician goes to the control room to request a clearance on the pump.  The next day the electrician unwires the motor.  They complete the maintenance order at the end of the day and send it back up to the A Foreman.

The completed electric maintenance order is sent back to the mechanics letting them know that the motor for the pump has been unwired.  When they receive it, a couple of days later, they schedule some time that week to go work on the pump.  At that time, they bring the motor to the electric shop so that it can be worked on at the same time.

The motor and the pump is worked on some time during the next week.

A machinist is needed to re-sleeve a bearing housing on either the motor or the pump or both.  So, an M.O. is created for the machinist to work on creating a sleeve in an end bell of the motor or the pump.

Gary (Stick) McCain

Gary (Stick) McCain — Machinist Extraordinaire

The electricians inform the mechanics when the motor is ready.  When they are done with the pump, and they have put it back in place, they put the motor back.  Then they create an M.O. for the Machinist to line up the motor and the pump before the coupling is installed.

The Machinists prioritize their work and at some point, let’s say a couple of days, they make it up to the motor and work on aligning the pump and the motor.

During the re-installation, it is decided that a bracket that has worn out needs to be welded back.  So, an M.O. is created for the welders to replace the bracket before the motor can be rewired.

The welders prioritize their work, and in a week (or two) they finally have time to go weld the bracket.

George Clouse

George Clouse – Welding Wizard

They return their M.O. completed to the mechanics who then tell the electricians that they can re-wire the motor.

The electricians prioritize their work and when they have time to go re-wire the motor, they wire it up.  After wiring it, they go to the control room to have the operators help them bump test the motor to make sure it runs in the right direction.  An entire day goes by until the electrician receives a call saying that the operator is ready to bump test the motor.  The electrician and/or mechanic meets the operator at the pump to bump test the motor.  Once this test is performed, the mechanic re-couples the motor.

The electrician then removes his clearance on the pump and it is put back into service.  The M.O.s are completed.

—  End here.  The time it took to repair the pump and put it back in service would commonly take one month —

Now see what happens when you have a cross-functional team working on it….(and be amazed).

— Start here —

The maintenance team receives a ticket (M.O.) from the planner that a pump is broken at the coal yard.  A mechanic goes and looks at it and determines it needs to be repaired.  He calls his Electrician Teammate and tells him that the motor needs to be unwired in order to fix the pump.  The electrician goes to the control room and takes a clearance on the pump.

The electrician then goes to the switchgear and waits for the operator to place the clearance.  When that is completed, the electrician goes to the pump and unwires the motor.  While there, he helps the mechanic pull the motor and put it aside.  The electrician determines there if the motor needs to be worked on.  If possible, it is repaired in place, or the motor is brought to the electric shop at the same time as the pump.  It is determined that the pump needs to be worked on, so they work together to bring it to the shop where the mechanics work on the pump.  Any machinist work is done at that time.

When the pump is being put back in place, the bracket is found broken, so they call the welder on their team who comes up and welds it back on.  The machinist comes with the electrician and the mechanic to align the motor.  The operators are called to bump test the motor.  As soon as the test is over, the coupling is installed.  The clearance is removed and the pump is put back in place.

— End here.  The pump can now be repaired within one week instead of four weeks.  Often the pump can be repaired in days instead of weeks. —

The reason why the cross-functional teams worked so well is that we all had the same priority.  We all had the same job and we had all the skills on our team to do all the work.  This was a fantastic change from working in silos.

This was “Working Smarter”, not “Working Harder”.  Ever since that day when we first learned that we had to “Work Harder” I always cringe when I hear that phrase.  To me, “Working Harder” means, “Working Dumber”.  Today I am a big advocate of Cross-Functional Teams.  I have seen them work successfully.  There was only one catch which I will talk about later.  This worked beautifully, but keep in mind… We had cross-functional teams made of the best Power Plant Men on the planet!  So, I may have a lopsided view of how successful they really work in the general public.